Permitting Authorities / City of Royal Oak - Building Department (Building Inspection)

Do you need a permit to replace a roof in Royal Oak, MI?

Adopted code

City of Royal Oak - Building Department (Building Inspection)

Yes, a permit is required to replace a roof in Royal Oak, MI, issued by City of Royal Oak - Building Department (Building Inspection). In Royal Oak, Building Inspection issues the permits for residential construction, and the city says "Visit www.accessmygov.com for online permitting and inspection requests." The page says "Create an account to apply for permits, pay fees, and schedule inspections." A PIN to link an account to the City of Royal Oak comes from the Building Department at 248-246-3210 between 8:00 am and 4:30 pm. The city's Master Administrative Fee Schedule, effective July 1, 2025, lists a "Residential 1 & 2 Family Building Permit Fee" priced by construction value with a $100 minimum, and no separate roofing item; the residential schedule printed for work under the Michigan Residential Code, effective 6/28/2016, reads "$12.00 per $1,000 of estimated cost of construction or fraction thereof" with a "Minimum Building Permit Fee: $100.00". Code questions go to an inspector: "Specific Code questions may be addressed to an Inspector, Monday through Friday, 8-9 a.m. or 3:30- 4:30 p.m." The Building Department is at 203 S Troy Street, Royal Oak, MI 48067, phone 248-246-3210; City Hall hours are Monday to Thursday 8:00 a.m. to 4:30 p.m. and Friday 8:00 a.m. to Noon.

Roof code checklist: Royal Oak, MI

ItemAnswerCode citeSourceVerified
Permit to replace a roofYesromi.gov2026-10-10
Repair permit thresholdPublishedromi.gov2026-10-10
Layer limit / roof-overPublishedR908.3.1.1codes.iccsafe.org2026-10-10
Deck & sheathingPublishedR905.2.1codes.iccsafe.org2026-10-10
Drip edgeYesR905.2.8.5codes.iccsafe.org2026-10-10
Ice & water shieldYesR905.1.2ars.apps.lara.state.mi.us2026-10-10
Mid-roof inspectionNot published
Impact-resistant (Class 4) roofingNoars.apps.lara.state.mi.us2026-10-10
Wind design criteriaNot published
Adopted codePublishedSec. 260-1ars.apps.lara.state.mi.us2026-10-10
Contractor license / registrationYeslegislature.mi.gov2026-10-10
Sales & use taxPublishedlegislature.mi.gov2026-10-10

Each row comes from the sourced record on this page; full wording is in the table below. "Not published" means no official source for that item was found when the record was last verified.

Jurisdiction
City of Royal Oak, Michigan
Jurisdiction type
city
Address
203 S Troy Street, Royal Oak, MI 48067
Contact
  • url: https://www.romi.gov/176/Building-Inspection
  • phone: 248-246-3210
Permit portal
Roofing permit required
Required
Contractor registration required
Required
Registration details
  • state_level: Michigan licenses residential maintenance and alteration contractors under the Occupational Code, and that licence "includes the following crafts and trades" among which it names roofing (MCL 339.2404(3)); "A person shall not engage in or attempt to engage in the practice of an occupation regulated under this act" without the licence (MCL 339.601(1)). MCL 339.2403 lists who may work without one, including a project whose "aggregate contract price for the labor, material, and any other items for the undertaking or project is less than $600.00". This record does not decide whether a given roofer falls inside an exemption.
  • city_level: The Building Inspection page lists a "Contractor Registration Form" among its documents. The form loads only in a web browser and its terms are not stated on the pages read for this record, so this record does not describe them; the Code of Ordinances chapters read (260, 400, 425 and 556) contain no contractor licence.
Permit process note
In Royal Oak, Building Inspection issues the permits for residential construction, and the city says "Visit www.accessmygov.com for online permitting and inspection requests." The page says "Create an account to apply for permits, pay fees, and schedule inspections." A PIN to link an account to the City of Royal Oak comes from the Building Department at 248-246-3210 between 8:00 am and 4:30 pm. The city's Master Administrative Fee Schedule, effective July 1, 2025, lists a "Residential 1 & 2 Family Building Permit Fee" priced by construction value with a $100 minimum, and no separate roofing item; the residential schedule printed for work under the Michigan Residential Code, effective 6/28/2016, reads "$12.00 per $1,000 of estimated cost of construction or fraction thereof" with a "Minimum Building Permit Fee: $100.00". Code questions go to an inspector: "Specific Code questions may be addressed to an Inspector, Monday through Friday, 8-9 a.m. or 3:30- 4:30 p.m." The Building Department is at 203 S Troy Street, Royal Oak, MI 48067, phone 248-246-3210; City Hall hours are Monday to Thursday 8:00 a.m. to 4:30 p.m. and Friday 8:00 a.m. to Noon.
Adopted code
2015 Michigan Residential Code. This is state law and it is the same in every Michigan city, village, township and county: the state construction code act says "This act and the code apply throughout the state," and the Michigan Residential Code rule adopts "the international residential code, 2015 edition" with the state amendments in R 408.30500 to R 408.30547g. A 2021 edition was filed with the secretary of state in 2025 but has not taken effect. On July 7, 2025 the Michigan Court of Claims entered a stipulated order in Home Builders Assoc et al. v LARA et al., and the Michigan Department of Licensing and Regulatory Affairs (LARA) says that while that order remains in place "the 2015 versions of the IRC and residential provisions of the IECC standards currently adopted, in part, by each rule set will remain valid and in effect." LARA's Statewide Jurisdiction List names the City of Royal Oak as its own building code enforcer. Section 260-1 of the city's Code of Ordinances designates the Building Official as the enforcing agency under the state construction code act and names no code edition, and the Building Department's pages read for this record name none.
Drip edge
Required — Required on asphalt shingle roofs by state law. Michigan makes no amendment to the drip edge rule of the 2015 International Residential Code, Section R905.2.8.5, which applies as published: "A drip edge shall be provided at eaves and rake edges of shingle roofs." Segments overlap by at least 2 inches, the drip edge extends at least 1/4 inch below the roof sheathing and at least 2 inches back onto the deck, it is fastened at no more than 12 inches on center, and underlayment goes over it at the eaves and under it at the rakes. A reroof is held to the same rule, because "Materials and methods of application used for re-covering or replacing an existing roof covering shall comply with the requirements of Chapter 9" (R908.1). The City of Royal Oak Building Inspection page, its fee schedules and Chapters 260, 400 and 556 of its Code of Ordinances were read for a local rule and state nothing further on drip edge. About drip edge
Ice & water shield
Required — Required everywhere in Michigan by state law. Michigan fills in the climatic design table of the 2015 code once for the whole state (Rule 516, Table R301.2(1)), and its ice barrier underlayment column reads Yes. The state footnote calls for Yes "for areas where the average daily temperature in January is 25 degrees Fahrenheit" or less, or where ice damming has caused damage. The base code then requires an ice barrier "for asphalt shingles, metal roof shingles, mineral-surfaced roll roofing, slate and slate-type shingles, wood shingles and wood shakes," running "from the lowest edges of all roof surfaces to a point not less than 24 inches (610 mm) inside the exterior wall line of the building" (R905.1.2). Detached accessory structures without conditioned floor area are exempt. On a tear-off, an existing ice barrier that is adhered to the deck may stay and be covered with an additional layer (R908.3, Exception). The City of Royal Oak Building Inspection page, its fee schedules and Chapters 260, 400 and 556 of its Code of Ordinances were read for a local rule and state nothing further on ice barrier. About ice & water barrier
Impact-resistant roofing
Not required — No impact-resistance requirement under state law. The 2015 Michigan Residential Code was searched in full and has no hail or impact rating rule for roof coverings: the words hail, impact and UL 2218 do not appear in it, and none of them appears in the roof assemblies chapter of the base 2015 International Residential Code either. Michigan applies one code statewide ("This act and the code apply throughout the state."), and the act gives the power to amend it to the state director, who adopts the model codes "with amendments, additions, or deletions as the director determines appropriate." The City of Royal Oak Building Inspection page, its fee schedules and Chapters 260, 400 and 556 of its Code of Ordinances state no impact rule.
Repair permit threshold
The City of Royal Oak's Building Department pages read for this record (Building Division, Building Inspection and its staff directory) and its fee schedules say nothing about reroofing and state no size, square or dollar point below which roof work needs no permit. They say only that Building Inspection "is responsible for issuing permits for commercial and residential construction projects" and refer questions to the department: "Any other questions can be directed to the Building Department at 248-246-3210." The city's Master Administrative Fee Schedule has no roofing line and prices a 1 and 2 family building permit by construction value. The state part: Michigan's construction code act says "A building permit is not required for ordinary repairs of a building or structure" and does not define ordinary repairs. For a small repair or a reroof, call the Building Department (248-246-3210) before starting.
Roof layer limit / recover
Two layers at most, under state law. Michigan builds one- and two-family homes to the 2015 Michigan Residential Code, which adopts the 2015 International Residential Code and makes no amendment to its reroofing section, Section R908; the Michigan rule set was searched in full and R908 does not appear in it. The base section therefore applies as the International Code Council publishes it. Section R908.3.1.1 lists the conditions under which a new roof may not be laid over an existing one, and the third is "Where the existing roof has two or more applications of any type of roof covering." One existing layer may be covered once; a roof that already carries two layers is torn off to the deck. The same section also bars covering a roof that is water soaked or too deteriorated to serve as a base, and covering "slate, clay, cement or asbestos-cement tile." Locally, the city's building ordinance, Chapter 260 (Construction Code Enforcement), was read in full, together with Chapter 400 (Housing) and Chapter 556 (Property Maintenance): they designate the enforcing agency and a Construction Code Board of Appeals, adopt the state housing law and a property maintenance code, and have no reroofing provision. Nothing local amends Section R908.
Deck & sheathing requirements
State law, from the base code. Michigan makes no amendment to the roof sheathing section of the 2015 International Residential Code, Section R803, which does not appear in the Michigan rule set, so it applies as published. Lumber roof sheathing follows Table R803.1: over rafters or beams 24 inches apart it must be at least 5/8 inch net thick. Wood structural panels must be identified "for grade, bond classification and performance category by a grade mark or certificate of inspection issued by an approved agency," and their spans may not exceed "the values set forth in Table R503.2.1.1(1), or APA E30." For a shingle roof the base code adds that "Asphalt shingles shall be fastened to solidly sheathed decks" (R905.2.1), and on any reroof "The structural roof components shall be capable of supporting the roof covering system" (R908.2). The City of Royal Oak Building Inspection page, its fee schedules and Chapters 260, 400 and 556 of its Code of Ordinances were read for a local rule and state nothing further on roof decks or sheathing.
Sales & use tax
6%, statewide, with no local add-on. This is state law: the General Sales Tax Act sets the tax "equal to 6% of the gross proceeds of the business," the Use Tax Act sets "a total combined rate equal to 6%," and the Michigan Department of Treasury says "Michigan does not allow city or local units to impose sales tax." On a roofing job the roofer is the taxpayer on materials, because the Use Tax Act counts as a consumer "A person acquiring tangible personal property if engaged in the business of constructing, altering, repairing, or improving the real estate of others." The same 6% applies throughout the City of Royal Oak.

The City of Royal Oak's Building Department, at 203 S Troy Street, issues permits for commercial and residential construction through its Building Inspection division and takes permit applications and inspection requests online. Chapter 260 of the city's Code of Ordinances designates the Building Official as the enforcing agency under the state construction code act, and the State of Michigan's jurisdiction list names the City as its own building code enforcer. Michigan applies one residential code statewide, so for houses the rules below are state law.

Working an insurance claim in Royal Oak, MI? Everything on this page (drip edge, ice & water shield, inspections, Class 4 rules) formatted as a claim-ready evidence pack: verbatim ordinance quotes, code section cites, verification dates, and official source links, ready to attach to a supplement. See a real sample pack (PDF, 4 pages, free).

Code items like drip edge and ice & water shield are what adjusters ask you to document.

Buy this jurisdiction's pack: $12 Delivered by email within minutes. Digital download: all sales are final once delivered, except for a failed delivery, a defective file, a duplicate purchase, or a pack materially different from its description. See Section 6 of our Terms of Use.

Questions about the Royal Oak, MI pack?

Not ready to buy, or need a different jurisdiction? Tell us and we’ll reply directly.

By submitting, you agree to our Terms of Use and Privacy Policy.

Sources

Roofing questions: Royal Oak, MI

Do you need a permit to replace a roof in Royal Oak, MI?

Yes, a permit is required to replace a roof in Royal Oak, MI. The City of Royal Oak's Building Department pages read for this record (Building Division, Building Inspection and its staff directory) and its fee schedules say nothing about reroofing and state no size, square or dollar point below which roof work needs no permit. They say only that Building Inspection "is responsible for issuing permits for commercial and residential construction projects" and refer questions to the department: "Any other questions can be directed to the Building Department at 248-246-3210." The city's Master Administrative Fee Schedule has no roofing line and prices a 1 and 2 family building permit by construction value. The state part: Michigan's construction code act says "A building permit is not required for ordinary repairs of a building or structure" and does not define ordinary repairs. For a small repair or a reroof, call the Building Department (248-246-3210) before starting.

Is ice & water shield required in Royal Oak, MI?

Yes. Required everywhere in Michigan by state law. Michigan fills in the climatic design table of the 2015 code once for the whole state (Rule 516, Table R301.2(1)), and its ice barrier underlayment column reads Yes. The state footnote calls for Yes "for areas where the average daily temperature in January is 25 degrees Fahrenheit" or less, or where ice damming has caused damage. The base code then requires an ice barrier "for asphalt shingles, metal roof shingles, mineral-surfaced roll roofing, slate and slate-type shingles, wood shingles and wood shakes," running "from the lowest edges of all roof surfaces to a point not less than 24 inches (610 mm) inside the exterior wall line of the building" (R905.1.2). Detached accessory structures without conditioned floor area are exempt. On a tear-off, an existing ice barrier that is adhered to the deck may stay and be covered with an additional layer (R908.3, Exception). The City of Royal Oak Building Inspection page, its fee schedules and Chapters 260, 400 and 556 of its Code of Ordinances were read for a local rule and state nothing further on ice barrier.

Is drip edge required in Royal Oak, MI?

Yes. Required on asphalt shingle roofs by state law. Michigan makes no amendment to the drip edge rule of the 2015 International Residential Code, Section R905.2.8.5, which applies as published: "A drip edge shall be provided at eaves and rake edges of shingle roofs." Segments overlap by at least 2 inches, the drip edge extends at least 1/4 inch below the roof sheathing and at least 2 inches back onto the deck, it is fastened at no more than 12 inches on center, and underlayment goes over it at the eaves and under it at the rakes. A reroof is held to the same rule, because "Materials and methods of application used for re-covering or replacing an existing roof covering shall comply with the requirements of Chapter 9" (R908.1). The City of Royal Oak Building Inspection page, its fee schedules and Chapters 260, 400 and 556 of its Code of Ordinances were read for a local rule and state nothing further on drip edge.

Can you roof over an existing roof in Royal Oak, MI?

Two layers at most, under state law. Michigan builds one- and two-family homes to the 2015 Michigan Residential Code, which adopts the 2015 International Residential Code and makes no amendment to its reroofing section, Section R908; the Michigan rule set was searched in full and R908 does not appear in it. The base section therefore applies as the International Code Council publishes it. Section R908.3.1.1 lists the conditions under which a new roof may not be laid over an existing one, and the third is "Where the existing roof has two or more applications of any type of roof covering." One existing layer may be covered once; a roof that already carries two layers is torn off to the deck. The same section also bars covering a roof that is water soaked or too deteriorated to serve as a base, and covering "slate, clay, cement or asbestos-cement tile." Locally, the city's building ordinance, Chapter 260 (Construction Code Enforcement), was read in full, together with Chapter 400 (Housing) and Chapter 556 (Property Maintenance): they designate the enforcing agency and a Construction Code Board of Appeals, adopt the state housing law and a property maintenance code, and have no reroofing provision. Nothing local amends Section R908.

Do roofing contractors need a license or registration in Royal Oak, MI?

Yes.

What building code does Royal Oak, MI use?

2015 Michigan Residential Code. This is state law and it is the same in every Michigan city, village, township and county: the state construction code act says "This act and the code apply throughout the state," and the Michigan Residential Code rule adopts "the international residential code, 2015 edition" with the state amendments in R 408.30500 to R 408.30547g. A 2021 edition was filed with the secretary of state in 2025 but has not taken effect. On July 7, 2025 the Michigan Court of Claims entered a stipulated order in Home Builders Assoc et al. v LARA et al., and the Michigan Department of Licensing and Regulatory Affairs (LARA) says that while that order remains in place "the 2015 versions of the IRC and residential provisions of the IECC standards currently adopted, in part, by each rule set will remain valid and in effect." LARA's Statewide Jurisdiction List names the City of Royal Oak as its own building code enforcer. Section 260-1 of the city's Code of Ordinances designates the Building Official as the enforcing agency under the state construction code act and names no code edition, and the Building Department's pages read for this record name none.