Permitting Authorities / Missouri / City of Lake Waukomis - City Hall (Building Permits)
Do you need a permit to replace a roof in Lake Waukomis, MO?
Adopted code
City of Lake Waukomis - City Hall (Building Permits)
Yes, a permit is required to replace a roof in Lake Waukomis, MO, issued by City of Lake Waukomis - City Hall (Building Permits). The City's Building Permits page lists "ROOF - $100" with the line "Permit is needed but no other paperwork is required". The City's Building Permit Process sheet lists "Roofing or reroofing" among items requiring a building permit. The page states: "All building permits must be approved by the building inspector prior to beginning work." and asks applicants to "drop it off in the drop box outside City Hall or come in during office hours with the required drawings/plans and fee". The page says "FEES MUST ACCOMPANY YOUR APPLICATIONS", gives "5 (FIVE) BUSINESS DAYS for review and approval", and notes that the Lake Waukomis Home Owners Association has a Deed of Restrictions which may restrict what home owners can do with their property.
Jurisdiction
City of Lake Waukomis, Missouri
Address
1147 NW South Shore Drive, Lake Waukomis, MO 64151
Contact
- url: https://www.lakewaukomis.org/permits-licenses
- phone: 816-741-2079
Roofing permit required
Required
Registration details
- state_level: Missouri has no statewide roofing contractor licence: the index of Chapter 324 of the Revised Statutes of Missouri, the chapter on occupations and professions, lists no section on roofing contractors.
- city_level: The City's permit page states: "Any contractor or home owner performing work in the City of Lake Waukomis that would require a building permit must apply for a Business License." The Building Permit Process sheet states: "Contractors and or Subcontractors must have a Lake Waukomis Business License". The page adds: "You must apply for the license at least 5 (FIVE) days prior to starting any work".
Permit process note
The City's Building Permits page lists "ROOF - $100" with the line "Permit is needed but no other paperwork is required". The City's Building Permit Process sheet lists "Roofing or reroofing" among items requiring a building permit. The page states: "All building permits must be approved by the building inspector prior to beginning work." and asks applicants to "drop it off in the drop box outside City Hall or come in during office hours with the required drawings/plans and fee". The page says "FEES MUST ACCOMPANY YOUR APPLICATIONS", gives "5 (FIVE) BUSINESS DAYS for review and approval", and notes that the Lake Waukomis Home Owners Association has a Deed of Restrictions which may restrict what home owners can do with their property.
Adopted code
RSMo 67.280 lets a community with the power to do so adopt a technical code by reference: "Any community, if the community otherwise has the power under the law to adopt such an ordinance, may adopt or repeal an ordinance which incorporates by reference the provisions of any code or portions of any code". The City's permit page states, for new homes, "Plans must meet the 2021 IBC Code Book" and, for decks, "All decks, footings, handrails, and stairs must conform to the 2021 IRC building codes". The City's ice barrier letter states: "The City adopted the requirement for new roofs form the 2012 IRC code book." The City's Building Permit Process sheet points to Title V, Chapter 500, Section 500.030 of its code on eCode360. This record did not read the City's code ordinance or amendments.
Ice & water shield
Required — The City's ice barrier letter states: "The City of Lake Waukomis requires ice barriers on new roofs." It cites 2012 IRC R905.2.7.1. This rests on the City's letter, not on a filled-in Table R301.2(1), which this record did not read.
About ice & water barrier
Sales & use tax
Lake Waukomis' combined sales tax rate is 6.475% (use tax the same), jurisdiction code 40322-165-000, per the Missouri Department of Revenue's Jurisdiction and Total Rate Database for the fourth quarter of 2026. Missouri's own state rate is 4.225%; the rest is local. Sales tax follows "the combined state and local rate at the location of the seller", so this rate applies to purchases from a seller in the town. For a re-roof, 12 CSR 10-112.010(1) provides that "a contractor is the final user and consumer of the materials and supplies used and consumed in fulfilling a construction contract and which become part of a completed real property improvement," so, in general, the roofer pays tax when it buys the materials. Under 12 CSR 10-112.010(3)(A), "In general, title passes after installation is complete, unless the contractor and purchaser expressly agree otherwise." Where title passes after attachment the contractor "is subject to tax on its purchase of the tangible personal property and does not collect tax on its transfer of ownership or title of the item." Where it passes before attachment the contractor "does not pay tax on its purchase, but must collect tax on the sale price of the item."
Local roofing hub
More roof permit pages in Missouri
Related guides
City Hall takes building permit applications in the City of Lake Waukomis, Missouri (Platte County); the City's site footer gives 1147 NW South Shore Drive as the address. The City's permit page and ice barrier letter name the 2021 IBC, the 2021 IRC and the 2012 IRC in different contexts. This listing covers the office's contact details, the local sales tax rate, the City's business licence rule, and the code and permit facts quoted below; it does not cover every local permit rule.