Permitting Authorities / Huerfano County Land Use and Building Department

Do you need a permit to replace a roof in Huerfano County, CO?

Adopted code

Huerfano County Land Use and Building Department

The building permit and contractor licensing authority for unincorporated Huerfano County, Colorado (Walsenburg area). Requires a Huerfano County contractor license to perform construction work, with a dedicated "D type Roofing" specialty-trade license category requiring ICC certification. Building permits are processed online through the SmartGov portal.

Jurisdiction
Huerfano County, Colorado
Jurisdiction type
county
Address
Walsenburg, CO 81089
Contact
  • url: https://huerfano.us/departments/land-use/
  • phone: 719-738-1220
  • email: [email protected]
Permit portal
Contractor registration required
Required
Registration details
  • license_types: ["A - Unlimited","B - Limited","C - Home Builder","D - Specialty Trade (includes a dedicated Roofing category, alongside Mechanical)"]
  • requirements: Copy of ICC certification (or equivalent) may be required for A, B, or C type licenses, and is required for D type Roofing and Mechanical licenses, plus liability insurance naming Huerfano County as certificate holder and worker's compensation coverage or a state waiver. New application fee $100 (non-refundable); license fee $100 per jurisdiction (Walsenburg or unincorporated county).
Permit process note
Building permit applications are submitted through the county's online SmartGov portal. Anyone applying for a permit who is not the property owner must hold a Huerfano County contractor license appropriate to the type of construction being permitted. Submittal packages that omit required documentation are typically returned.
Inspection requirements
Construction documents must demonstrate compliance with the adopted codes; the building official may require documents to be prepared by a registered design professional. Per county building-code design criteria, ice-shield underlayment is required above 6,200 feet elevation due to the possibility of ice jamming on roofs (IRC R905.1.2).
Adopted code
Huerfano County has adopted the 2021 editions of the International Building Code (with appendix chapters C and F), International Residential Code (with appendix chapters F, J, R, and S), International Mechanical Code, International Energy Conservation Code, International Fuel Gas Code, and International Existing Building Code, plus ICC 400-2022 (design and construction of log structures), pursuant to County Resolution 23-25.
Drip edge
Required — Huerfano County adopts the 2021 IRC by County Resolution 23-25. Read in full, Section 7's complete list of amendments contains no provision touching Chapter 9, Roof Assemblies, so the base 2021 IRC's drip-edge requirement for shingle roofs (Section R905.2.8.5) applies unmodified in unincorporated Huerfano County. About drip edge
Ice & water shield
Required — County Resolution 23-25, Section 7, amends IRC Table R301.2 (Climatic and Geographic Design Criteria) and, as printed in the resolution itself, that amended table adds an "Ice Barrier Underlayment Required" column reading "YES (apply to elevations above 6200 ft.)". This is a locally set table entry in the county's own adopted code, which turns on the base IRC's ice-barrier-membrane requirement (Section R905.1.2) for construction above that elevation across unincorporated Huerfano County. About ice & water barrier
Mid-roof inspection
Not required — The Huerfano County Building Regulations policy (Section 6, Building Permit Regulations, read in full) and the county's own Building Permits FAQ describe inspections only generically, by construction phase — for example footings, rebar and pier holes before pour, and framing before the frame is covered — and name no distinct mid-roof or dry-in inspection stage for roofing work in unincorporated Huerfano County.
Impact-resistant roofing
Not required — Neither County Resolution 23-25 (the county's adopting and amending instrument, read in full) nor the Huerfano County Building Regulations policy, the county's Building Permit Guidelines handout, or its Building Permits FAQ contains a UL 2218 or Class 4 impact-rating provision for roofing in unincorporated Huerfano County. The resolution's only locally set roof-related design criteria are wind speed, ground snow load, and the ice-barrier-underlayment elevation trigger; none of those instruments mentions hail or impact resistance, and no insurance-discount language appears in any of them either.
Repair permit threshold
Huerfano County adopts the 2021 IRC by County Resolution 23-25 (read in full: the recitals and Sections 1 through 9, including the complete Section 7 list of amendments, insertions, attachments and deletions). That list amends building-permit administration provisions (Sections 101, 103, 105, 106 through 113 of the IBC and R106 through R112 of the IRC) and Chapter 3's climatic-design table, but the only exempt-work change in it is deleting item ten of IBC Section 105.2 — the IRC's own R105.2 work-exempt-from-permit list is untouched. No dollar-value or percentage threshold distinguishing a minor roof repair from a permit- triggering re-roof is added anywhere in the resolution, so the base 2021 IRC's own R105.2 provisions apply unmodified in unincorporated Huerfano County. The county's own FAQ confirms a permit is required to reroof ("I need a roofing permit. Fill out a roofing/solar building permit, provide deed/proof of ownership...and a diagram of the roof.") but states no threshold of its own.
Wind design criteria
The Huerfano County Building Permit Guidelines (revised January 1, 2024, linked from the county's Land Use and Building page) print, "The following is an excerpt from the Huerfano County Building Code," a Climatic and Geographic Design Criteria table reading: Ground Snow Load "Resolution 23-25, Attachment 1"; Wind Speed "130 MPH Ultimate Design"; Seismic Design Category "B"; Weathering "Severe"; Frost Line Depth "Resolution 23-25, Attachment 1"; Termite "Moderate to Heavy"; Decay "Slight"; Winter Design Temp. "0° F"; Flood Hazards "See Section 1612.3-amended"; Air Freezing Index "2000"; Mean Annual Temp. "Walsenburg 51.3° F / Rye 46.6° F / Westcliffe 42.2° F." The table as printed carries no Ice Barrier Underlayment Required row or column.
Roof layer limit / recover
Huerfano County adopts the 2021 IRC by County Resolution 23-25. Read in full, Section 7's complete list of amendments, insertions, attachments and deletions touches permit administration, Chapter 3's climatic-design table, one fire-resistance footnote for airport hangars, ICF construction, and the county's energy-code (IECC) tables — it contains no amendment anywhere to Chapter 9, Roof Assemblies, of the IRC. So the base 2021 IRC's own provisions on the number of roof-covering layers permitted before tear-off apply unmodified in unincorporated Huerfano County. Base-code rule, read at 2021 IRC Section R908.3.1.1 (Roof recover not allowed) and quoted here rather than left behind the ICC paywall: a roof recover "shall not be permitted" where "the existing roof has two or more applications of any type of roof covering" (nor where the existing covering is water soaked or deteriorated, or is slate, clay, cement or asbestos-cement tile). One existing layer may therefore be recovered; a second existing layer forces tear-off to the deck.
Deck & sheathing requirements
Huerfano County adopts the 2021 IRC by County Resolution 23-25. Read in full, Section 7's complete list of amendments contains no provision touching roof deck sheathing or Chapter 9, Roof Assemblies, of the IRC, so the base 2021 IRC's own roof deck sheathing provisions apply unmodified in unincorporated Huerfano County.
Sales & use tax
5.9% combined (state 2.9% + Huerfano County 3%; no city component since this record covers unincorporated Huerfano County). The January 2026 DR 1002 "State-Collected Colorado County Sales Tax" table prints Huerfano County's rate as 3% with no county use tax. This corrects an earlier 4.9% figure taken from the June 2019 edition of DR 1002, which printed the county at 2%; the Colorado Department of Revenue still serves that 2019 edition at a live URL, so a working link is not evidence of a current rate. No special district in DR 1002's Special Districts tables names Huerfano County in its boundary description.

Working an insurance claim in Huerfano County, CO? Everything on this page — drip edge, ice & water shield, inspections, Class 4 rules — formatted as a claim-ready evidence pack: verbatim ordinance quotes, code section cites, verification dates, and official source links, ready to attach to a supplement. See a real sample pack (PDF) — one page, free.

Buy this jurisdiction's pack — $12 Delivered by email within minutes.

Questions about the Huerfano County, CO pack?

Not ready to buy, or need a different jurisdiction? Tell us and we’ll reply directly.

By submitting, you agree to our Terms of Use and Privacy Policy.

Sources

Free instant roof estimate — Huerfano County, CO

Ballpark your replacement in 20 seconds. No phone call required to see the number.

Roofing questions — Huerfano County, CO

When does a roof repair need a permit in Huerfano County, CO?

Huerfano County adopts the 2021 IRC by County Resolution 23-25 (read in full: the recitals and Sections 1 through 9, including the complete Section 7 list of amendments, insertions, attachments and deletions). That list amends building-permit administration provisions (Sections 101, 103, 105, 106 through 113 of the IBC and R106 through R112 of the IRC) and Chapter 3's climatic-design table, but the only exempt-work change in it is deleting item ten of IBC Section 105.2 — the IRC's own R105.2 work-exempt-from-permit list is untouched. No dollar-value or percentage threshold distinguishing a minor roof repair from a permit- triggering re-roof is added anywhere in the resolution, so the base 2021 IRC's own R105.2 provisions apply unmodified in unincorporated Huerfano County. The county's own FAQ confirms a permit is required to reroof ("I need a roofing permit. Fill out a roofing/solar building permit, provide deed/proof of ownership...and a diagram of the roof.") but states no threshold of its own.

Is ice & water shield required in Huerfano County, CO?

Required — County Resolution 23-25, Section 7, amends IRC Table R301.2 (Climatic and Geographic Design Criteria) and, as printed in the resolution itself, that amended table adds an "Ice Barrier Underlayment Required" column reading "YES (apply to elevations above 6200 ft.)". This is a locally set table entry in the county's own adopted code, which turns on the base IRC's ice-barrier-membrane requirement (Section R905.1.2) for construction above that elevation across unincorporated Huerfano County..

Is drip edge required?

Required — Huerfano County adopts the 2021 IRC by County Resolution 23-25. Read in full, Section 7's complete list of amendments contains no provision touching Chapter 9, Roof Assemblies, so the base 2021 IRC's drip-edge requirement for shingle roofs (Section R905.2.8.5) applies unmodified in unincorporated Huerfano County..

Is a mid-roof inspection required?

Not required — The Huerfano County Building Regulations policy (Section 6, Building Permit Regulations, read in full) and the county's own Building Permits FAQ describe inspections only generically, by construction phase — for example footings, rebar and pier holes before pour, and framing before the frame is covered — and name no distinct mid-roof or dry-in inspection stage for roofing work in unincorporated Huerfano County..

Do roofing contractors need a license or registration in Huerfano County, CO?

Required.

What building code does Huerfano County, CO use?

Huerfano County has adopted the 2021 editions of the International Building Code (with appendix chapters C and F), International Residential Code (with appendix chapters F, J, R, and S), International Mechanical Code, International Energy Conservation Code, International Fuel Gas Code, and International Existing Building Code, plus ICC 400-2022 (design and construction of log structures), pursuant to County Resolution 23-25.