Permitting Authorities / Missouri / City of Gower - Zoning Administrator

Do you need a permit to replace a roof in Gower, MO?

Adopted code

City of Gower - Zoning Administrator

Yes, a permit is required to replace a roof in Gower, MO, issued by City of Gower - Zoning Administrator. The City's Zoning and Building Permits page states: "The Zoning ordinance requires permits to construct, repair, alter, move and or demolish a structure." It adds: "The Zoning Administrator will issue all permits." The City's building permit form, headed "BUILDING PERMIT", lists Re-roof, gutters as numbered item 8 under "TYPE & COST OF PERMIT". The page also states: "Residents are subject to a $100.00 fine for not having a permit." The page also states: "Contact Zoning Administrator for specific permit amounts." The form's footer reads "City of Gower, Zoning Permit". The form states that a permit "shall expire after 180 days if no work is undertaken or such use or activity is not established.".

Jurisdiction
City of Gower, Missouri
Jurisdiction type
city
Address
97 North 4th Street, Gower, MO 64454
Contact
  • url: https://www.gowermo.com/zoning-building-permits
  • phone: 816-424-6617
Roofing permit required
Required
Permit process note
The City's Zoning and Building Permits page states: "The Zoning ordinance requires permits to construct, repair, alter, move and or demolish a structure." It adds: "The Zoning Administrator will issue all permits." The City's building permit form, headed "BUILDING PERMIT", lists Re-roof, gutters as numbered item 8 under "TYPE & COST OF PERMIT". The page also states: "Residents are subject to a $100.00 fine for not having a permit." The page also states: "Contact Zoning Administrator for specific permit amounts." The form's footer reads "City of Gower, Zoning Permit". The form states that a permit "shall expire after 180 days if no work is undertaken or such use or activity is not established."
Adopted code
RSMo 67.280 lets a community with the power to do so adopt a technical code by reference: "Any community, if the community otherwise has the power under the law to adopt such an ordinance, may adopt or repeal an ordinance which incorporates by reference the provisions of any code or portions of any code". This record did not read Gower's own code ordinance or amendments.
Sales & use tax
Gower's combined sales tax rate depends on the county part of the city: in its Clinton County part 8.475% (use tax 7.975%), jurisdiction code 28036-049-000; in its Buchanan County part 8.575% (use tax 8.075%), jurisdiction code 28036-021-000, per the Missouri Department of Revenue's Jurisdiction and Total Rate Database for the fourth quarter of 2026. Missouri's own state rate is 4.225%; the rest is local. Sales tax follows "the combined state and local rate at the location of the seller", so this rate applies to purchases from a seller in the town. For a re-roof, 12 CSR 10-112.010(1) provides that "a contractor is the final user and consumer of the materials and supplies used and consumed in fulfilling a construction contract and which become part of a completed real property improvement," so, in general, the roofer pays tax when it buys the materials. Under 12 CSR 10-112.010(3)(A), "In general, title passes after installation is complete, unless the contractor and purchaser expressly agree otherwise." Where title passes after attachment the contractor "is subject to tax on its purchase of the tangible personal property and does not collect tax on its transfer of ownership or title of the item." Where it passes before attachment the contractor "does not pay tax on its purchase, but must collect tax on the sale price of the item."

The Zoning Administrator issues building permits in the City of Gower, Missouri (Clinton and Buchanan counties), from City Hall at 97 North 4th Street, the address printed on the City's zoning application form. This listing covers the office's contact details, the local sales tax rate, and the permit facts quoted below; it does not cover every local permit rule.

Sources

Roofing questions: Gower, MO

Do you need a permit to replace a roof in Gower, MO?

Yes, a permit is required to replace a roof in Gower, MO.

What building code does Gower, MO use?

RSMo 67.280 lets a community with the power to do so adopt a technical code by reference: "Any community, if the community otherwise has the power under the law to adopt such an ordinance, may adopt or repeal an ordinance which incorporates by reference the provisions of any code or portions of any code". This record did not read Gower's own code ordinance or amendments.