Permitting Authorities / Township of Flowerfield - Zoning and Building Permits

Do you need a permit to replace a roof in Township of Flowerfield, MI?

Adopted code

Township of Flowerfield - Zoning and Building Permits

Yes, a permit is required to replace a roof in Township of Flowerfield, MI, issued by Township of Flowerfield - Zoning and Building Permits. Flowerfield Township's Applications-Permits page says "It is strongly suggested that you discuss your project prior to filling out the combined application" and gives the Zoning Administrator's number, 269-651-3130. The Combined Zoning and Building Permit Application says "Building or excavation work shall not be started until the application for permit has been approved by the Zoning Administrator and/or the Building Official" and "The building official will advise you of the building permit fees at the time of issuance of such permit." Electrical, plumbing, mechanical and demolition permits are separate applications posted on the same page. The Zoning Administration Office is at 65656 Burg Road, Sturgis, MI 49091. No building fee schedule was read.

Roof code checklist: Township of Flowerfield, MI

ItemAnswerCode citeSourceVerified
Permit to replace a roofYesflowerfieldtwp.net2026-10-15
Repair permit thresholdPublishedflowerfieldtwp.net2026-10-15
Layer limit / roof-overPublishedR908.3.1.1codes.iccsafe.org2026-10-15
Deck & sheathingPublishedR905.2.1codes.iccsafe.org2026-10-15
Drip edgeYesR905.2.8.5codes.iccsafe.org2026-10-15
Ice & water shieldYesR905.1.2ars.apps.lara.state.mi.us2026-10-15
Mid-roof inspectionNot published
Impact-resistant (Class 4) roofingNoars.apps.lara.state.mi.us2026-10-15
Wind design criteriaNot published
Adopted codePublishedars.apps.lara.state.mi.us2026-10-15
Contractor license / registrationYeslegislature.mi.gov2026-10-15
Sales & use taxPublishedlegislature.mi.gov2026-10-15

Each row comes from the sourced record on this page; full wording is in the table below. "Not published" means no official source for that item was found when the record was last verified.

Jurisdiction
Township of Flowerfield, St. Joseph County, Michigan
Jurisdiction type
city
Address
65656 Burg Road, Sturgis, MI 49091
Contact
  • url: https://flowerfieldtwp.net/applications-permits
  • phone: 269-651-3130
Roofing permit required
Required
Contractor registration required
Required
Permit process note
Flowerfield Township's Applications-Permits page says "It is strongly suggested that you discuss your project prior to filling out the combined application" and gives the Zoning Administrator's number, 269-651-3130. The Combined Zoning and Building Permit Application says "Building or excavation work shall not be started until the application for permit has been approved by the Zoning Administrator and/or the Building Official" and "The building official will advise you of the building permit fees at the time of issuance of such permit." Electrical, plumbing, mechanical and demolition permits are separate applications posted on the same page. The Zoning Administration Office is at 65656 Burg Road, Sturgis, MI 49091. No building fee schedule was read.
Adopted code
2015 Michigan Residential Code. This is state law and it is the same in every Michigan city, village, township and county: the state construction code act says "This act and the code apply throughout the state," and the Michigan Residential Code rule adopts "the international residential code, 2015 edition" with the state amendments in R 408.30500 to R 408.30547g. A 2021 edition was filed with the secretary of state in 2025 but has not taken effect. On July 7, 2025 the Michigan Court of Claims entered a stipulated order in Home Builders Assoc et al. v LARA et al., and the Michigan Department of Licensing and Regulatory Affairs (LARA) says that while that order remains in place "the 2015 versions of the IRC and residential provisions of the IECC standards currently adopted, in part, by each rule set will remain valid and in effect." LARA's Statewide Jurisdiction List names the Township of Flowerfield as its own building code enforcer. The township's Applications-Permits page and its Combined Zoning and Building Permit Application and Fee Schedule name no residential code edition; this record states the 2015 Michigan Residential Code for the reasons above.
Drip edge
Required — Required on asphalt shingle roofs by state law. Michigan makes no amendment to the drip edge rule of the 2015 International Residential Code, Section R905.2.8.5, which applies as published: "A drip edge shall be provided at eaves and rake edges of shingle roofs." Segments overlap by at least 2 inches, the drip edge extends at least 1/4 inch below the roof sheathing and at least 2 inches back onto the deck, it is fastened at no more than 12 inches on center, and underlayment goes over it at the eaves and under it at the rakes. A reroof is held to the same rule, because "Materials and methods of application used for re-covering or replacing an existing roof covering shall comply with the requirements of Chapter 9" (R908.1). The township's Applications-Permits page and its Combined Zoning and Building Permit Application and Fee Schedule were read for a local rule and state nothing further on drip edge. About drip edge
Ice & water shield
Required — Required everywhere in Michigan by state law. Michigan fills in the climatic design table of the 2015 code once for the whole state (Rule 516, Table R301.2(1)), and its ice barrier underlayment column reads Yes. The state footnote calls for Yes "for areas where the average daily temperature in January is 25 degrees Fahrenheit" or less, or where ice damming has caused damage. The base code then requires an ice barrier "for asphalt shingles, metal roof shingles, mineral-surfaced roll roofing, slate and slate-type shingles, wood shingles and wood shakes," running "from the lowest edges of all roof surfaces to a point not less than 24 inches (610 mm) inside the exterior wall line of the building" (R905.1.2). Detached accessory structures without conditioned floor area are exempt. On a tear-off, an existing ice barrier that is adhered to the deck may stay and be covered with an additional layer (R908.3, Exception). The township's Applications-Permits page and its Combined Zoning and Building Permit Application and Fee Schedule were read for a local rule and state nothing further on ice barrier. About ice & water barrier
Impact-resistant roofing
Not required — No impact-resistance requirement under state law. The 2015 Michigan Residential Code was searched in full and has no hail or impact rating rule for roof coverings: the words hail, impact and UL 2218 do not appear in it, and none of them appears in the roof assemblies chapter of the base 2015 International Residential Code either. Michigan applies one code statewide ("This act and the code apply throughout the state."), and the act gives the power to amend it to the state director, who adopts the model codes "with amendments, additions, or deletions as the director determines appropriate." The township's Applications-Permits page and its Combined Zoning and Building Permit Application and Fee Schedule were read for a local rule and state nothing further on impact resistance.
Repair permit threshold
No size or cost threshold is published for roof work. The township's Combined Zoning and Building Permit Application lists its types of improvement, from single family dwelling and shed to demolition, and does not name reroofing or roof repair. It says "Plans are not required for alterations and repair work if determined by the building official to be minor in nature." which is a plans rule and not a permit exemption. Under state law, "A building permit is not required for ordinary repairs of a building or structure." (MCL 125.1510), without a definition of ordinary repairs. The township has published nothing applying that relief to roof work, so ask its Zoning Administration Office (269-651-3130) before starting a small roof repair.
Roof layer limit / recover
Two layers at most, under state law. Michigan builds one- and two-family homes to the 2015 Michigan Residential Code, which adopts the 2015 International Residential Code and makes no amendment to its reroofing section, Section R908; the Michigan rule set was searched in full and R908 does not appear in it. The base section therefore applies as the International Code Council publishes it. Section R908.3.1.1 lists the conditions under which a new roof may not be laid over an existing one, and the third is "Where the existing roof has two or more applications of any type of roof covering." One existing layer may be covered once; a roof that already carries two layers is torn off to the deck. The same section also bars covering a roof that is water soaked or too deteriorated to serve as a base, and covering "slate, clay, cement or asbestos-cement tile." The township's permit page and combined application state no layer rule. Its building ordinance was not found and its zoning ordinance page was not read, so this record sets no layer classification.
Deck & sheathing requirements
State law, from the base code. Michigan makes no amendment to the roof sheathing section of the 2015 International Residential Code, Section R803, which does not appear in the Michigan rule set, so it applies as published. Lumber roof sheathing follows Table R803.1: over rafters or beams 24 inches apart it must be at least 5/8 inch net thick. Wood structural panels must be identified "for grade, bond classification and performance category by a grade mark or certificate of inspection issued by an approved agency," and their spans may not exceed "the values set forth in Table R503.2.1.1(1), or APA E30." For a shingle roof the base code adds that "Asphalt shingles shall be fastened to solidly sheathed decks" (R905.2.1), and on any reroof "The structural roof components shall be capable of supporting the roof covering system" (R908.2). The township's Applications-Permits page and its Combined Zoning and Building Permit Application and Fee Schedule were read for a local rule and state nothing further on roof sheathing.
Sales & use tax
6%, statewide, with no local add-on. This is state law: the General Sales Tax Act sets the tax "equal to 6% of the gross proceeds of the business," the Use Tax Act sets "a total combined rate equal to 6%," and the Michigan Department of Treasury says "Michigan does not allow city or local units to impose sales tax." On a roofing job the roofer is the taxpayer on materials, because the Use Tax Act counts as a consumer "A person acquiring tangible personal property if engaged in the business of constructing, altering, repairing, or improving the real estate of others." Nothing in the township's Applications-Permits page and its Combined Zoning and Building Permit Application and Fee Schedule changes this.

Flowerfield Township, in St. Joseph County, takes one Combined Zoning and Building Permit Application through its Zoning Administration Office, which works with a township building official. Michigan's single state construction code applies, and for houses that is the 2015 Michigan Residential Code.

Working an insurance claim in Township of Flowerfield, MI? Everything on this page (drip edge, ice & water shield, inspections, Class 4 rules) formatted as a claim-ready evidence pack: verbatim ordinance quotes, code section cites, verification dates, and official source links, ready to attach to a supplement. See a real sample pack (PDF, 4 pages, free).

Code items like drip edge and ice & water shield are what adjusters ask you to document.

Buy this jurisdiction's pack: $12 Delivered by email within minutes. Digital download: all sales are final once delivered, except for a failed delivery, a defective file, a duplicate purchase, or a pack materially different from its description. See Section 6 of our Terms of Use.

Questions about the Township of Flowerfield, MI pack?

Not ready to buy, or need a different jurisdiction? Tell us and we’ll reply directly.

By submitting, you agree to our Terms of Use and Privacy Policy.

Sources

Roofing questions: Township of Flowerfield, MI

Do you need a permit to replace a roof in Township of Flowerfield, MI?

Yes, a permit is required to replace a roof in Township of Flowerfield, MI. No size or cost threshold is published for roof work. The township's Combined Zoning and Building Permit Application lists its types of improvement, from single family dwelling and shed to demolition, and does not name reroofing or roof repair. It says "Plans are not required for alterations and repair work if determined by the building official to be minor in nature." which is a plans rule and not a permit exemption. Under state law, "A building permit is not required for ordinary repairs of a building or structure." (MCL 125.1510), without a definition of ordinary repairs. The township has published nothing applying that relief to roof work, so ask its Zoning Administration Office (269-651-3130) before starting a small roof repair.

Is ice & water shield required in Township of Flowerfield, MI?

Yes. Required everywhere in Michigan by state law. Michigan fills in the climatic design table of the 2015 code once for the whole state (Rule 516, Table R301.2(1)), and its ice barrier underlayment column reads Yes. The state footnote calls for Yes "for areas where the average daily temperature in January is 25 degrees Fahrenheit" or less, or where ice damming has caused damage. The base code then requires an ice barrier "for asphalt shingles, metal roof shingles, mineral-surfaced roll roofing, slate and slate-type shingles, wood shingles and wood shakes," running "from the lowest edges of all roof surfaces to a point not less than 24 inches (610 mm) inside the exterior wall line of the building" (R905.1.2). Detached accessory structures without conditioned floor area are exempt. On a tear-off, an existing ice barrier that is adhered to the deck may stay and be covered with an additional layer (R908.3, Exception). The township's Applications-Permits page and its Combined Zoning and Building Permit Application and Fee Schedule were read for a local rule and state nothing further on ice barrier.

Is drip edge required in Township of Flowerfield, MI?

Yes. Required on asphalt shingle roofs by state law. Michigan makes no amendment to the drip edge rule of the 2015 International Residential Code, Section R905.2.8.5, which applies as published: "A drip edge shall be provided at eaves and rake edges of shingle roofs." Segments overlap by at least 2 inches, the drip edge extends at least 1/4 inch below the roof sheathing and at least 2 inches back onto the deck, it is fastened at no more than 12 inches on center, and underlayment goes over it at the eaves and under it at the rakes. A reroof is held to the same rule, because "Materials and methods of application used for re-covering or replacing an existing roof covering shall comply with the requirements of Chapter 9" (R908.1). The township's Applications-Permits page and its Combined Zoning and Building Permit Application and Fee Schedule were read for a local rule and state nothing further on drip edge.

Can you roof over an existing roof in Township of Flowerfield, MI?

Two layers at most, under state law. Michigan builds one- and two-family homes to the 2015 Michigan Residential Code, which adopts the 2015 International Residential Code and makes no amendment to its reroofing section, Section R908; the Michigan rule set was searched in full and R908 does not appear in it. The base section therefore applies as the International Code Council publishes it. Section R908.3.1.1 lists the conditions under which a new roof may not be laid over an existing one, and the third is "Where the existing roof has two or more applications of any type of roof covering." One existing layer may be covered once; a roof that already carries two layers is torn off to the deck. The same section also bars covering a roof that is water soaked or too deteriorated to serve as a base, and covering "slate, clay, cement or asbestos-cement tile." The township's permit page and combined application state no layer rule. Its building ordinance was not found and its zoning ordinance page was not read, so this record sets no layer classification.

Do roofing contractors need a license or registration in Township of Flowerfield, MI?

Yes.

What building code does Township of Flowerfield, MI use?

2015 Michigan Residential Code. This is state law and it is the same in every Michigan city, village, township and county: the state construction code act says "This act and the code apply throughout the state," and the Michigan Residential Code rule adopts "the international residential code, 2015 edition" with the state amendments in R 408.30500 to R 408.30547g. A 2021 edition was filed with the secretary of state in 2025 but has not taken effect. On July 7, 2025 the Michigan Court of Claims entered a stipulated order in Home Builders Assoc et al. v LARA et al., and the Michigan Department of Licensing and Regulatory Affairs (LARA) says that while that order remains in place "the 2015 versions of the IRC and residential provisions of the IECC standards currently adopted, in part, by each rule set will remain valid and in effect." LARA's Statewide Jurisdiction List names the Township of Flowerfield as its own building code enforcer. The township's Applications-Permits page and its Combined Zoning and Building Permit Application and Fee Schedule name no residential code edition; this record states the 2015 Michigan Residential Code for the reasons above.