Do you need a permit to replace a roof in Brighton, MI?

Adopted code

City of Brighton - Community Development, Building Department

Yes, a permit is required to replace a roof in Brighton, MI, issued by City of Brighton - Community Development, Building Department. In the City of Brighton a reroof needs a city permit: the Building and Permits page says "Below is a list including, but not limited to, types of work that require a permit from the City of Brighton prior to work occurring" and lists "Roofing of any kind" and "Siding". The permit is requested on the city's Building/Sign/Demo Permit Application, which asks for the estimated project cost and lists "Roof" among the residential types of improvement, with the submittal requirements "Residential - Three (3) sets of complete folded building plans drawn to scale." and "Contractor's driver's license, proof of insurance and builder's license if applicable." The page says "There is a penalty for working without a permit and it is enforced." and "A $200.00 fine will be assessed for residential work without a permit". For questions about permits, the page says to "contact the City of Brighton Building Department at" 810-225-8019. The Livingston County Building Department issues the mechanical, plumbing and electrical permits, and the city's FAQ says "Livingston County Building Department completes inspections, their Inspection Request Line: 517-546-3830". No online permit portal is posted on the page, and the city's fee schedule prints the Building Department fees in a layout that does not read reliably, so ask for the current fee.

Roof code checklist: Brighton, MI

ItemAnswerCode citeSourceVerified
Permit to replace a roofYesbrightoncitymi.gov2026-10-11
Repair permit thresholdPublishedbrightoncitymi.gov2026-10-11
Layer limit / roof-overPublishedR908.3.1.1codes.iccsafe.org2026-10-11
Deck & sheathingPublishedR905.2.1codes.iccsafe.org2026-10-11
Drip edgeYesR905.2.8.5codes.iccsafe.org2026-10-11
Ice & water shieldYesR905.1.2ars.apps.lara.state.mi.us2026-10-11
Mid-roof inspectionNot published
Impact-resistant (Class 4) roofingNoars.apps.lara.state.mi.us2026-10-11
Wind design criteriaNot published
Adopted codePublishedSec. 18-26ars.apps.lara.state.mi.us2026-10-11
Contractor license / registrationYeslegislature.mi.gov2026-10-11
Sales & use taxPublishedlegislature.mi.gov2026-10-11

Each row comes from the sourced record on this page; full wording is in the table below. "Not published" means no official source for that item was found when the record was last verified.

Jurisdiction
City of Brighton, Michigan
Jurisdiction type
city
Address
200 North First Street, Brighton, MI 48116
Contact
  • url: https://www.brightoncitymi.gov/services___departments/community_development/building_and_permits.php
  • phone: 810-225-8019
Roofing permit required
Required
Contractor registration required
Required
Registration details
  • state_level: Michigan licenses residential maintenance and alteration contractors under the Occupational Code, and that licence "includes the following crafts and trades" among which it names roofing (MCL 339.2404(3)); "A person shall not engage in or attempt to engage in the practice of an occupation regulated under this act" without the licence (MCL 339.601(1)). MCL 339.2403 lists who may work without one, including a project whose "aggregate contract price for the labor, material, and any other items for the undertaking or project is less than $600.00". This record does not decide whether a given roofer falls inside an exemption.
  • city_level: The City of Brighton's Building/Sign/Demo Permit Application lists as a submittal requirement the "Contractor's driver's license, proof of insurance and builder's license if applicable." The Building and Permits page and the Chapter 18 text name no separate city contractor registration. This record does not decide whether a given roofer falls inside a state exemption.
Permit process note
In the City of Brighton a reroof needs a city permit: the Building and Permits page says "Below is a list including, but not limited to, types of work that require a permit from the City of Brighton prior to work occurring" and lists "Roofing of any kind" and "Siding". The permit is requested on the city's Building/Sign/Demo Permit Application, which asks for the estimated project cost and lists "Roof" among the residential types of improvement, with the submittal requirements "Residential - Three (3) sets of complete folded building plans drawn to scale." and "Contractor's driver's license, proof of insurance and builder's license if applicable." The page says "There is a penalty for working without a permit and it is enforced." and "A $200.00 fine will be assessed for residential work without a permit". For questions about permits, the page says to "contact the City of Brighton Building Department at" 810-225-8019. The Livingston County Building Department issues the mechanical, plumbing and electrical permits, and the city's FAQ says "Livingston County Building Department completes inspections, their Inspection Request Line: 517-546-3830". No online permit portal is posted on the page, and the city's fee schedule prints the Building Department fees in a layout that does not read reliably, so ask for the current fee.
Adopted code
2015 Michigan Residential Code. This is state law and it is the same in every Michigan city, village, township and county: the state construction code act says "This act and the code apply throughout the state," and the Michigan Residential Code rule adopts "the international residential code, 2015 edition" with the state amendments in R 408.30500 to R 408.30547g. A 2021 edition was filed with the secretary of state in 2025 but has not taken effect. On July 7, 2025 the Michigan Court of Claims entered a stipulated order in Home Builders Assoc et al. v LARA et al., and the Michigan Department of Licensing and Regulatory Affairs (LARA) says that while that order remains in place "the 2015 versions of the IRC and residential provisions of the IECC standards currently adopted, in part, by each rule set will remain valid and in effect." LARA's Statewide Jurisdiction List names the City of Brighton as its own building code enforcer. The city's Building and Permits page lists "The existing codes being enforced in the City of Brighton" and names the "2015 MI Residential Code" among them. Section 18-26 of the city's Code of Ordinances designates the planning and development department as the enforcing agency and names no edition.
Drip edge
Required — Required on asphalt shingle roofs by state law. Michigan makes no amendment to the drip edge rule of the 2015 International Residential Code, Section R905.2.8.5, which applies as published: "A drip edge shall be provided at eaves and rake edges of shingle roofs." Segments overlap by at least 2 inches, the drip edge extends at least 1/4 inch below the roof sheathing and at least 2 inches back onto the deck, it is fastened at no more than 12 inches on center, and underlayment goes over it at the eaves and under it at the rakes. A reroof is held to the same rule, because "Materials and methods of application used for re-covering or replacing an existing roof covering shall comply with the requirements of Chapter 9" (R908.1). The City of Brighton's Building and Permits page and its Building/Sign/Demo Permit Application were read for a local rule and state nothing further on drip edge, and Chapter 18 (Buildings and Building Regulations) of the City's Code of Ordinances was read in full and has no provision on it. About drip edge
Ice & water shield
Required — Required everywhere in Michigan by state law. Michigan fills in the climatic design table of the 2015 code once for the whole state (Rule 516, Table R301.2(1)), and its ice barrier underlayment column reads Yes. The state footnote calls for Yes "for areas where the average daily temperature in January is 25 degrees Fahrenheit" or less, or where ice damming has caused damage. The base code then requires an ice barrier "for asphalt shingles, metal roof shingles, mineral-surfaced roll roofing, slate and slate-type shingles, wood shingles and wood shakes," running "from the lowest edges of all roof surfaces to a point not less than 24 inches (610 mm) inside the exterior wall line of the building" (R905.1.2). Detached accessory structures without conditioned floor area are exempt. On a tear-off, an existing ice barrier that is adhered to the deck may stay and be covered with an additional layer (R908.3, Exception). The City of Brighton's Building and Permits page and its Building/Sign/Demo Permit Application were read for a local rule and state nothing further on ice barrier, and Chapter 18 (Buildings and Building Regulations) of the City's Code of Ordinances was read in full and has no provision on it. About ice & water barrier
Impact-resistant roofing
Not required — No impact-resistance requirement under state law. The 2015 Michigan Residential Code was searched in full and has no hail or impact rating rule for roof coverings: the words hail, impact and UL 2218 do not appear in it, and none of them appears in the roof assemblies chapter of the base 2015 International Residential Code either. Michigan applies one code statewide ("This act and the code apply throughout the state."), and the act gives the power to amend it to the state director, who adopts the model codes "with amendments, additions, or deletions as the director determines appropriate." The City of Brighton's Building and Permits page and its Building/Sign/Demo Permit Application were read for a local rule and state nothing further on impact resistance, and Chapter 18 (Buildings and Building Regulations) of the City's Code of Ordinances was read in full and has no provision on it.
Repair permit threshold
No size or cost threshold is published. The City of Brighton's Building and Permits page says "Below is a list including, but not limited to, types of work that require a permit from the City of Brighton prior to work occurring" and the list includes "Roofing of any kind". The city's Building/Sign/Demo Permit Application lists "Roof" among the residential types of improvement. Under state law, "A building permit is not required for ordinary repairs of a building or structure." (MCL 125.1510), without a definition of ordinary repairs.
Roof layer limit / recover
Two layers at most, under state law. Michigan builds one- and two-family homes to the 2015 Michigan Residential Code, which adopts the 2015 International Residential Code and makes no amendment to its reroofing section, Section R908; the Michigan rule set was searched in full and R908 does not appear in it. The base section therefore applies as the International Code Council publishes it. Section R908.3.1.1 lists the conditions under which a new roof may not be laid over an existing one, and the third is "Where the existing roof has two or more applications of any type of roof covering." One existing layer may be covered once; a roof that already carries two layers is torn off to the deck. The same section also bars covering a roof that is water soaked or too deteriorated to serve as a base, and covering "slate, clay, cement or asbestos-cement tile." Locally, Chapter 18 (Buildings and Building Regulations) of the City of Brighton Code of Ordinances was read in full, all 59 sections from 18-26 to 18-114: it designates the enforcing agency, deals with unsafe structures, adopts the International Property Maintenance Code, enforces Appendix G of the Michigan Building Code for flood hazard areas and regulates rental registration and vacant buildings; it has no reroofing provision and amends nothing in Section R908. The City's Building and Permits page states no layer rule.
Deck & sheathing requirements
State law, from the base code. Michigan makes no amendment to the roof sheathing section of the 2015 International Residential Code, Section R803, which does not appear in the Michigan rule set, so it applies as published. Lumber roof sheathing follows Table R803.1: over rafters or beams 24 inches apart it must be at least 5/8 inch net thick. Wood structural panels must be identified "for grade, bond classification and performance category by a grade mark or certificate of inspection issued by an approved agency," and their spans may not exceed "the values set forth in Table R503.2.1.1(1), or APA E30." For a shingle roof the base code adds that "Asphalt shingles shall be fastened to solidly sheathed decks" (R905.2.1), and on any reroof "The structural roof components shall be capable of supporting the roof covering system" (R908.2). The City of Brighton's Building and Permits page and its Building/Sign/Demo Permit Application were read for a local rule and state nothing further on roof sheathing, and Chapter 18 (Buildings and Building Regulations) of the City's Code of Ordinances was read in full and has no provision on it.
Sales & use tax
6%, statewide, with no local add-on. This is state law: the General Sales Tax Act sets the tax "equal to 6% of the gross proceeds of the business," the Use Tax Act sets "a total combined rate equal to 6%," and the Michigan Department of Treasury says "Michigan does not allow city or local units to impose sales tax." On a roofing job the roofer is the taxpayer on materials, because the Use Tax Act counts as a consumer "A person acquiring tangible personal property if engaged in the business of constructing, altering, repairing, or improving the real estate of others." Nothing on the City of Brighton's Building and Permits page changes this.

The City of Brighton's Community Development Department, at City Hall at 200 North First Street, administers the city's building permits, and its Building and Permits page lists roofing of any kind among the work that needs a city permit. The city's Code of Ordinances designates its planning and development department as the enforcing agency under the state construction code act, and the State of Michigan's Statewide Jurisdiction List names the City of Brighton as its own building code enforcer. Michigan's single state construction code applies, and for houses that is the 2015 Michigan Residential Code.

Working an insurance claim in Brighton, MI? Everything on this page (drip edge, ice & water shield, inspections, Class 4 rules) formatted as a claim-ready evidence pack: verbatim ordinance quotes, code section cites, verification dates, and official source links, ready to attach to a supplement. See a real sample pack (PDF, 4 pages, free).

Code items like drip edge and ice & water shield are what adjusters ask you to document.

Buy this jurisdiction's pack: $12 Delivered by email within minutes. Digital download: all sales are final once delivered, except for a failed delivery, a defective file, a duplicate purchase, or a pack materially different from its description. See Section 6 of our Terms of Use.

Questions about the Brighton, MI pack?

Not ready to buy, or need a different jurisdiction? Tell us and we’ll reply directly.

By submitting, you agree to our Terms of Use and Privacy Policy.

Sources

Roofing questions: Brighton, MI

Do you need a permit to replace a roof in Brighton, MI?

Yes, a permit is required to replace a roof in Brighton, MI. No size or cost threshold is published. The City of Brighton's Building and Permits page says "Below is a list including, but not limited to, types of work that require a permit from the City of Brighton prior to work occurring" and the list includes "Roofing of any kind". The city's Building/Sign/Demo Permit Application lists "Roof" among the residential types of improvement. Under state law, "A building permit is not required for ordinary repairs of a building or structure." (MCL 125.1510), without a definition of ordinary repairs.

Is ice & water shield required in Brighton, MI?

Yes. Required everywhere in Michigan by state law. Michigan fills in the climatic design table of the 2015 code once for the whole state (Rule 516, Table R301.2(1)), and its ice barrier underlayment column reads Yes. The state footnote calls for Yes "for areas where the average daily temperature in January is 25 degrees Fahrenheit" or less, or where ice damming has caused damage. The base code then requires an ice barrier "for asphalt shingles, metal roof shingles, mineral-surfaced roll roofing, slate and slate-type shingles, wood shingles and wood shakes," running "from the lowest edges of all roof surfaces to a point not less than 24 inches (610 mm) inside the exterior wall line of the building" (R905.1.2). Detached accessory structures without conditioned floor area are exempt. On a tear-off, an existing ice barrier that is adhered to the deck may stay and be covered with an additional layer (R908.3, Exception). The City of Brighton's Building and Permits page and its Building/Sign/Demo Permit Application were read for a local rule and state nothing further on ice barrier, and Chapter 18 (Buildings and Building Regulations) of the City's Code of Ordinances was read in full and has no provision on it.

Is drip edge required in Brighton, MI?

Yes. Required on asphalt shingle roofs by state law. Michigan makes no amendment to the drip edge rule of the 2015 International Residential Code, Section R905.2.8.5, which applies as published: "A drip edge shall be provided at eaves and rake edges of shingle roofs." Segments overlap by at least 2 inches, the drip edge extends at least 1/4 inch below the roof sheathing and at least 2 inches back onto the deck, it is fastened at no more than 12 inches on center, and underlayment goes over it at the eaves and under it at the rakes. A reroof is held to the same rule, because "Materials and methods of application used for re-covering or replacing an existing roof covering shall comply with the requirements of Chapter 9" (R908.1). The City of Brighton's Building and Permits page and its Building/Sign/Demo Permit Application were read for a local rule and state nothing further on drip edge, and Chapter 18 (Buildings and Building Regulations) of the City's Code of Ordinances was read in full and has no provision on it.

Can you roof over an existing roof in Brighton, MI?

Two layers at most, under state law. Michigan builds one- and two-family homes to the 2015 Michigan Residential Code, which adopts the 2015 International Residential Code and makes no amendment to its reroofing section, Section R908; the Michigan rule set was searched in full and R908 does not appear in it. The base section therefore applies as the International Code Council publishes it. Section R908.3.1.1 lists the conditions under which a new roof may not be laid over an existing one, and the third is "Where the existing roof has two or more applications of any type of roof covering." One existing layer may be covered once; a roof that already carries two layers is torn off to the deck. The same section also bars covering a roof that is water soaked or too deteriorated to serve as a base, and covering "slate, clay, cement or asbestos-cement tile." Locally, Chapter 18 (Buildings and Building Regulations) of the City of Brighton Code of Ordinances was read in full, all 59 sections from 18-26 to 18-114: it designates the enforcing agency, deals with unsafe structures, adopts the International Property Maintenance Code, enforces Appendix G of the Michigan Building Code for flood hazard areas and regulates rental registration and vacant buildings; it has no reroofing provision and amends nothing in Section R908. The City's Building and Permits page states no layer rule.

Do roofing contractors need a license or registration in Brighton, MI?

Yes.

What building code does Brighton, MI use?

2015 Michigan Residential Code. This is state law and it is the same in every Michigan city, village, township and county: the state construction code act says "This act and the code apply throughout the state," and the Michigan Residential Code rule adopts "the international residential code, 2015 edition" with the state amendments in R 408.30500 to R 408.30547g. A 2021 edition was filed with the secretary of state in 2025 but has not taken effect. On July 7, 2025 the Michigan Court of Claims entered a stipulated order in Home Builders Assoc et al. v LARA et al., and the Michigan Department of Licensing and Regulatory Affairs (LARA) says that while that order remains in place "the 2015 versions of the IRC and residential provisions of the IECC standards currently adopted, in part, by each rule set will remain valid and in effect." LARA's Statewide Jurisdiction List names the City of Brighton as its own building code enforcer. The city's Building and Permits page lists "The existing codes being enforced in the City of Brighton" and names the "2015 MI Residential Code" among them. Section 18-26 of the city's Code of Ordinances designates the planning and development department as the enforcing agency and names no edition.