Yes, a permit is required to replace a roof in Township of Bainbridge, MI, issued by Bainbridge Township - Building Department. In Bainbridge Township a reroof is permit work: the Building Department page says "Building Permits are required for any new construction, siding, roofing or renovation projects." The building inspector, who is also the zoning administrator, is in the office Tuesday and Thursday from 8:00 am to 10:00 am and can be reached at (269) 468-8040. The township's building and zoning fee schedule, which the page links as its 2025 schedule and which is headed 2024, sets building permit fees by valuation, starting at $22.00 for a valuation of $1.00 to $500.00 and $22.00 for the first $500.00 plus $2.75 for each additional $100.00 from $501.00 to $2,000.00, and lists a separate $50.00 zoning permit fee for re-roofing, window replacement and re-siding. The township's building permit application is a one-page form that asks for the contractor's residential builder's license number.
Roof code checklist: Township of Bainbridge, MI
Each row comes from the sourced record on this page; full wording is in the table below. "Not published" means no official source for that item was found when the record was last verified.
Jurisdiction
Township of Bainbridge, Berrien County, Michigan
Address
7315 Territorial Road, Watervliet, MI 49098
Contact
- url: https://bainbridgetownship.org/township-officials/building-department/
- phone: 269-468-8040
Roofing permit required
Required
Contractor registration required
Required
Permit process note
In Bainbridge Township a reroof is permit work: the Building Department page says "Building Permits are required for any new construction, siding, roofing or renovation projects." The building inspector, who is also the zoning administrator, is in the office Tuesday and Thursday from 8:00 am to 10:00 am and can be reached at (269) 468-8040. The township's building and zoning fee schedule, which the page links as its 2025 schedule and which is headed 2024, sets building permit fees by valuation, starting at $22.00 for a valuation of $1.00 to $500.00 and $22.00 for the first $500.00 plus $2.75 for each additional $100.00 from $501.00 to $2,000.00, and lists a separate $50.00 zoning permit fee for re-roofing, window replacement and re-siding. The township's building permit application is a one-page form that asks for the contractor's residential builder's license number.
Adopted code
2015 Michigan Residential Code. This is state law and it is the same in every Michigan city, village, township and county: the state construction code act says "This act and the code apply throughout the state," and the Michigan Residential Code rule adopts "the international residential code, 2015 edition" with the state amendments in R 408.30500 to R 408.30547g. A 2021 edition was filed with the secretary of state in 2025 but has not taken effect. On July 7, 2025 the Michigan Court of Claims entered a stipulated order in Home Builders Assoc et al. v LARA et al., and the Michigan Department of Licensing and Regulatory Affairs (LARA) says that while that order remains in place "the 2015 versions of the IRC and residential provisions of the IECC standards currently adopted, in part, by each rule set will remain valid and in effect." LARA's Statewide Jurisdiction List names the Township of Bainbridge as its own building code enforcer. The Building Department page lists "2015 Michigan Residential Code" among the codes the department operates under, and Ordinance No. 38B, adopted May 9, 2016, begins "Pursuant to the provisions of the 2015 Residential Code" and adopts that code's amendments by reference. Bainbridge Township's Ordinance No. 38 (adopted July 2, 2001) adopts amendments to the "Michigan Building Code, 2000", which names no residential code edition; that code text was not read, and this record states the 2015 Michigan Residential Code for the reasons above.
Drip edge
Required — Required on asphalt shingle roofs by state law. Michigan makes no amendment to the drip edge rule of the 2015 International Residential Code, Section R905.2.8.5, which applies as published: "A drip edge shall be provided at eaves and rake edges of shingle roofs." Segments overlap by at least 2 inches, the drip edge extends at least 1/4 inch below the roof sheathing and at least 2 inches back onto the deck, it is fastened at no more than 12 inches on center, and underlayment goes over it at the eaves and under it at the rakes. A reroof is held to the same rule, because "Materials and methods of application used for re-covering or replacing an existing roof covering shall comply with the requirements of Chapter 9" (R908.1). The Bainbridge Township Building Department page and the township's Ordinance Nos. 37A, 38, 38A, 38B, 39, 42, 50A and 54 were read for a local rule and state nothing further on drip edge.
About drip edge
Ice & water shield
Required — Required everywhere in Michigan by state law. Michigan fills in the climatic design table of the 2015 code once for the whole state (Rule 516, Table R301.2(1)), and its ice barrier underlayment column reads Yes. The state footnote calls for Yes "for areas where the average daily temperature in January is 25 degrees Fahrenheit" or less, or where ice damming has caused damage. The base code then requires an ice barrier "for asphalt shingles, metal roof shingles, mineral-surfaced roll roofing, slate and slate-type shingles, wood shingles and wood shakes," running "from the lowest edges of all roof surfaces to a point not less than 24 inches (610 mm) inside the exterior wall line of the building" (R905.1.2). Detached accessory structures without conditioned floor area are exempt. On a tear-off, an existing ice barrier that is adhered to the deck may stay and be covered with an additional layer (R908.3, Exception). The Bainbridge Township Building Department page and the township's Ordinance Nos. 37A, 38, 38A, 38B, 39, 42, 50A and 54 were read for a local rule and state nothing further on ice barrier.
About ice & water barrier
Impact-resistant roofing
Not required — No impact-resistance requirement under state law. The 2015 Michigan Residential Code was searched in full and has no hail or impact rating rule for roof coverings: the words hail, impact and UL 2218 do not appear in it, and none of them appears in the roof assemblies chapter of the base 2015 International Residential Code either. Michigan applies one code statewide ("This act and the code apply throughout the state."), and the act gives the power to amend it to the state director, who adopts the model codes "with amendments, additions, or deletions as the director determines appropriate." The Bainbridge Township Building Department page and the township's Ordinance Nos. 37A, 38, 38A, 38B, 39, 42, 50A and 54 were read for a local rule and state nothing further on impact resistance.
Repair permit threshold
Bainbridge Township's Building Department says "Building Permits are required for any new construction, siding, roofing or renovation projects." The township's fee schedule also carries a dedicated $50.00 zoning permit fee line for re-roofing, window replacement and re-siding. Under state law, "A building permit is not required for ordinary repairs of a building or structure." (MCL 125.1510), without a definition of ordinary repairs.
Roof layer limit / recover
Two layers at most, under state law. Michigan builds one- and two-family homes to the 2015 Michigan Residential Code, which adopts the 2015 International Residential Code and makes no amendment to its reroofing section, Section R908; the Michigan rule set was searched in full and R908 does not appear in it. The base section therefore applies as the International Code Council publishes it. Section R908.3.1.1 lists the conditions under which a new roof may not be laid over an existing one, and the third is "Where the existing roof has two or more applications of any type of roof covering." One existing layer may be covered once; a roof that already carries two layers is torn off to the deck. The same section also bars covering a roof that is water soaked or too deteriorated to serve as a base, and covering "slate, clay, cement or asbestos-cement tile." Locally, the township's building ordinances listed on its Ordinances page (Ordinance Nos. 37A, 38, 38A, 38B, 39, 42, 50A and 54) were read: they adopt codes and statutes by reference, and the only roof text in them is the property maintenance code's roof clause, "The roof and flashing shall be sound, tight and not have defects that admit rain"; none amends anything in Section R908. The Building Department page and fee schedule state no layer rule.
Deck & sheathing requirements
State law, from the base code. Michigan makes no amendment to the roof sheathing section of the 2015 International Residential Code, Section R803, which does not appear in the Michigan rule set, so it applies as published. Lumber roof sheathing follows Table R803.1: over rafters or beams 24 inches apart it must be at least 5/8 inch net thick. Wood structural panels must be identified "for grade, bond classification and performance category by a grade mark or certificate of inspection issued by an approved agency," and their spans may not exceed "the values set forth in Table R503.2.1.1(1), or APA E30." For a shingle roof the base code adds that "Asphalt shingles shall be fastened to solidly sheathed decks" (R905.2.1), and on any reroof "The structural roof components shall be capable of supporting the roof covering system" (R908.2). The Bainbridge Township Building Department page and the township's Ordinance Nos. 37A, 38, 38A, 38B, 39, 42, 50A and 54 were read for a local rule and state nothing further on roof sheathing.
Sales & use tax
6%, statewide, with no local add-on. This is state law: the General Sales Tax Act sets the tax "equal to 6% of the gross proceeds of the business," the Use Tax Act sets "a total combined rate equal to 6%," and the Michigan Department of Treasury says "Michigan does not allow city or local units to impose sales tax." On a roofing job the roofer is the taxpayer on materials, because the Use Tax Act counts as a consumer "A person acquiring tangible personal property if engaged in the business of constructing, altering, repairing, or improving the real estate of others." Nothing on the Bainbridge Township Building Department page changes this.
Local roofing hub
Roof permits nearby: Berrien County
Related guides
Bainbridge Township's Building Department, at the township hall at 7315 Territorial Road in Watervliet, issues building permits in Berrien County, and its building inspector, who is also the zoning administrator, is in the office Tuesday and Thursday from 8:00 to 10:00 a.m. The department's page says "Building Permits are required for any new construction, siding, roofing or renovation projects." Michigan's single state construction code applies, and for houses that is the 2015 Michigan Residential Code.
Working an insurance claim in Township of Bainbridge, MI? Everything on this page (drip edge, ice & water shield, inspections, Class 4 rules) formatted as a claim-ready evidence pack: verbatim ordinance quotes, code section cites, verification dates, and official source links, ready to attach to a supplement. See a real sample pack (PDF, 4 pages, free).
Code items like drip edge and ice & water shield are what adjusters ask you to document.
Buy this jurisdiction's pack: $12 Delivered by email within minutes. Digital download: all sales are final once delivered, except for a failed delivery, a defective file, a duplicate purchase, or a pack materially different from its description. See Section 6 of our Terms of Use.
Questions about the Township of Bainbridge, MI pack?
Not ready to buy, or need a different jurisdiction? Tell us and we’ll reply directly.
Roofing questions: Township of Bainbridge, MI
Do you need a permit to replace a roof in Township of Bainbridge, MI?
Yes, a permit is required to replace a roof in Township of Bainbridge, MI. Bainbridge Township's Building Department says "Building Permits are required for any new construction, siding, roofing or renovation projects." The township's fee schedule also carries a dedicated $50.00 zoning permit fee line for re-roofing, window replacement and re-siding. Under state law, "A building permit is not required for ordinary repairs of a building or structure." (MCL 125.1510), without a definition of ordinary repairs.
Is ice & water shield required in Township of Bainbridge, MI?
Yes. Required everywhere in Michigan by state law. Michigan fills in the climatic design table of the 2015 code once for the whole state (Rule 516, Table R301.2(1)), and its ice barrier underlayment column reads Yes. The state footnote calls for Yes "for areas where the average daily temperature in January is 25 degrees Fahrenheit" or less, or where ice damming has caused damage. The base code then requires an ice barrier "for asphalt shingles, metal roof shingles, mineral-surfaced roll roofing, slate and slate-type shingles, wood shingles and wood shakes," running "from the lowest edges of all roof surfaces to a point not less than 24 inches (610 mm) inside the exterior wall line of the building" (R905.1.2). Detached accessory structures without conditioned floor area are exempt. On a tear-off, an existing ice barrier that is adhered to the deck may stay and be covered with an additional layer (R908.3, Exception). The Bainbridge Township Building Department page and the township's Ordinance Nos. 37A, 38, 38A, 38B, 39, 42, 50A and 54 were read for a local rule and state nothing further on ice barrier.
Is drip edge required in Township of Bainbridge, MI?
Yes. Required on asphalt shingle roofs by state law. Michigan makes no amendment to the drip edge rule of the 2015 International Residential Code, Section R905.2.8.5, which applies as published: "A drip edge shall be provided at eaves and rake edges of shingle roofs." Segments overlap by at least 2 inches, the drip edge extends at least 1/4 inch below the roof sheathing and at least 2 inches back onto the deck, it is fastened at no more than 12 inches on center, and underlayment goes over it at the eaves and under it at the rakes. A reroof is held to the same rule, because "Materials and methods of application used for re-covering or replacing an existing roof covering shall comply with the requirements of Chapter 9" (R908.1). The Bainbridge Township Building Department page and the township's Ordinance Nos. 37A, 38, 38A, 38B, 39, 42, 50A and 54 were read for a local rule and state nothing further on drip edge.
Can you roof over an existing roof in Township of Bainbridge, MI?
Two layers at most, under state law. Michigan builds one- and two-family homes to the 2015 Michigan Residential Code, which adopts the 2015 International Residential Code and makes no amendment to its reroofing section, Section R908; the Michigan rule set was searched in full and R908 does not appear in it. The base section therefore applies as the International Code Council publishes it. Section R908.3.1.1 lists the conditions under which a new roof may not be laid over an existing one, and the third is "Where the existing roof has two or more applications of any type of roof covering." One existing layer may be covered once; a roof that already carries two layers is torn off to the deck. The same section also bars covering a roof that is water soaked or too deteriorated to serve as a base, and covering "slate, clay, cement or asbestos-cement tile." Locally, the township's building ordinances listed on its Ordinances page (Ordinance Nos. 37A, 38, 38A, 38B, 39, 42, 50A and 54) were read: they adopt codes and statutes by reference, and the only roof text in them is the property maintenance code's roof clause, "The roof and flashing shall be sound, tight and not have defects that admit rain"; none amends anything in Section R908. The Building Department page and fee schedule state no layer rule.
Do roofing contractors need a license or registration in Township of Bainbridge, MI?
Yes.
What building code does Township of Bainbridge, MI use?
2015 Michigan Residential Code. This is state law and it is the same in every Michigan city, village, township and county: the state construction code act says "This act and the code apply throughout the state," and the Michigan Residential Code rule adopts "the international residential code, 2015 edition" with the state amendments in R 408.30500 to R 408.30547g. A 2021 edition was filed with the secretary of state in 2025 but has not taken effect. On July 7, 2025 the Michigan Court of Claims entered a stipulated order in Home Builders Assoc et al. v LARA et al., and the Michigan Department of Licensing and Regulatory Affairs (LARA) says that while that order remains in place "the 2015 versions of the IRC and residential provisions of the IECC standards currently adopted, in part, by each rule set will remain valid and in effect." LARA's Statewide Jurisdiction List names the Township of Bainbridge as its own building code enforcer. The Building Department page lists "2015 Michigan Residential Code" among the codes the department operates under, and Ordinance No. 38B, adopted May 9, 2016, begins "Pursuant to the provisions of the 2015 Residential Code" and adopts that code's amendments by reference. Bainbridge Township's Ordinance No. 38 (adopted July 2, 2001) adopts amendments to the "Michigan Building Code, 2000", which names no residential code edition; that code text was not read, and this record states the 2015 Michigan Residential Code for the reasons above.